Capital Project

Capital Project

Bus Garage Progress

Phase One Scope:
•Mill and removal of parking lot asphalt to be graded and paved.
•New SMT (Storm Management Trench) including drywells.
•Conduit install for electric entrance gate, future EV bus, and restoration of existing perimeter pedestal outlets.
•New fence to include a mow strip for clean look and low maintenance.
•Grading - topsoil/seeding.
•Main entrance gate install.
•Fence mow strip.
•Rear lot bollards.


Greenlawn Progress

Phase One Scope:
•Mill and removal of asphalt from tennis court.
•Demolition of the handball court.
•New SMT (Storm Management Trench) including drywells and flat drain underneath the court area.
•New 12’ court fence as well a 6’ fence along school property perimeter.
•Removal of old fuel tank and installation of new tank and monitoring system.
•Privacy & tennis court fence. 
•Grading - topsoil/seeding.
•Sidewalk
•Court painting

Guilford Progress

Phase One Scope:
•Sidewalk demolition with new sidewalk installed to curb of front entrance.
•New SMT (Storm Management Trench) including drywells along new sidewalk.
•Removal of old fuel tank and installation of new tank and monitoring system.
•Electric removed from poles on back side of school for eventual trenching. 
*Complete*




Capital Project News

The Evening Sun Interviews Superintendent Timothy Ryan

Mr. Ryan sat down with Sarah Genter from The Evening Sun to discuss our upcoming Capital Project.  See the article below! 